View Categories

Move One Series to a Different Date

Use this when: one schedule needs to run on a different date or time, and everything else about it is fine.

Don’t use this when: you want to change how often it repeats — that’s a feed setting. See Change the Schedule for Existing Series.


Steps #

  1. Open GravityOps → Recurring Submissions → Queue and find the series. (Or open the parent entry and use the card’s Change next submission button, which opens Queue in a new tab.)
  2. Click Change next submission.
  3. Enter the full next date and time.
  4. Click Preview and read the continuing cadence it projects.
  5. Save.

What Changes, and What Doesn’t #

✅ Changes ❌ Stays the same
The next target The recurrence interval
The anchor the following occurrences are counted from Progress and successful counts
The end condition and its limit
Attempt history
The paused state — this does not resume a series

The cadence continues from the date and time you chose. Set a weekly series to next Thursday and it runs every Thursday after that.


Common Uses #

Pull the first occurrence earlier #

A new schedule always puts its first occurrence a full interval out. If a daily feed saved at 01:14 should run today at 01:20 rather than tomorrow, start the series and then move its next submission to today.

Shift a run off a holiday #

Move that one occurrence to the next working day. Subsequent runs follow from there.

Re-align a series that drifted #

If a manual run put a series out of step with its siblings, set the target you want and the rhythm re-anchors.


When the Button Isn’t There #

Situation Why What to do
Series is completed or canceled There is no next occurrence Use Start Series From Now
Series is locked Something is submitting it right now Wait for the attempt to finish
Series is processing Same Wait
Records need review after a storage failure Submissions are blocked to prevent duplicates Review the child entries and attempt history first

Paused and failed series can have their next submission changed — but changing it does not restart them. Use Resume for that.


Doing This for Many Series #

There is no bulk date editor. For many series on the same feed, either:

  • edit the feed and apply the saved schedule to existing series, which recalculates future targets for the whole set, or
  • move each series individually when the dates genuinely differ.

Bulk per-series actions are on the roadmap.